Each SecureSheet project follows the same basic implementation steps to drive you to a successful launch of your process that is being supported by a SecureSheet.  During project kick-off, the SecureSheet Customer Success team reviews the SecureSheet Implementation Plan to set milestone dates and initiate first steps for the project.  The Implementation Plan is set up as a SecureSheet itself, found in your organization's SecureSheet site for on-going reference throughout the project, and is able to be updated by any SecureSheet administrator in your organization.


Find a PDF of the SecureSheet Year 1 Process here.


NOTE:  You will need a PDF viewer in order to open this file. If you do not have a PDF viewer or are unsure or unable to download one, please check with your organization's technical support team for assistance.

Year 1 Process


Step


Description

 Expected Timeframe

Team  Responsibility

Help Topic Links

1.0

Kick-off

Client reviews their compensation planning business requirements with the SecureSheet team.

Week 1

Both


1.1


Planning timeline

Identify milestones including start date, testing start date, manager training date, system open date, lockout dates, statement distribution date, system freeze date.

Week 1

Client


1.2


Employee population

Describe employee population including size and geographic distribution.

Week 1

Client


1.3


Data update cycle

Discuss data management while system is open to managers.

Week 1

Client

1.4


Administrators and key users

Identify system administrators on client side as well as any other key users or contacts.

Week 1

Client


2.0

Review Excel Structure

Client adds 5 columns to the left of the existing Excel file, reserved for SecureSheet processing. Client uploads Excel file(s) currently used to support compensation process to File Attachments section of SecureSheet site.

Week 1

Client

2.1


Validate initial file load in SecureSheet

SecureSheet loads initial Excel file.

Week 1

SecureSheet


3.0

Set Up Working Model

SecureSheet team uploads "Users-Views" SecureSheet for Client to define views and column settings per view, and identify users and their security permissions.

Weeks 1 and 2

Both

3.1


Complete Users-Views Input

Import filled in "Users-Views".

Weeks 1 and 2

Client

3.2


Create SecureSheet working model

Create a working model based on "Users-Views" input for Client review.

Weeks 1 and 2

SecureSheet


3.3


Review working model

Client does initial testing and provides feedback on working model.  Client and SecureSheet incorporate changes.

Weeks 1 and 2

Both

3.4


Review user list

Review user list, security and business process roles, and impersonators (if applicable).

Weeks 1 and 2

Client

3.5


Review submission process

Finalize submission timelines (lock dates on Views).

Weeks 1 and 2

Client

3.6


Review summary information

Confirm format and calculations for summary totals in header rows. Setup Summary views (if applicable).

Weeks 1 and 2

Both

4.0

Single-Sign On setup (if required)

SecureSheet provides SSO instructions, metadata file, and whitelist instructions.

Client provides their metadata file with authentication certificate. SecureSheet and Client configure respective side and test.

Weeks 1 and 2

Client

5.0

Compensation Statement design review

Client provides Compensation Statement(s) that support their end-of-cycle communication process.

Review Statement(s) to ensure all data fields are on the main SecureSheet.

Week 1 or 2

Client

5.1


Compensation Statement(s) set up

SecureSheet team sets up Statement Template(s) and Views.

Client map columns from main planning tab to the appropriate locations in the Statement Template(s).

Weeks 2, 3, and 4

Both

5.2


Review Compensation Statement(s)

Client reviews Compensation Statement(s) for formatting and accuracy.

Weeks 3 and 4

Client


6.0

On-line Review Meetings

SecureSheet team hosts review meetings of the working model and the Compensation Statement(s), and transfers knowledge for testing phase.

Ongoing

Both


7.0

Client Testing

Client validates user experience by impersonating different users based on role (e.g., Manager, Director, VP, Executive, HRBP) for the following: 

- views

- security

- formulas

- summary totals

- submission/approval process

- statements

Weeks 2, 3 and 4

Client


7.1


SecureSheet updates

Iterative Client review. SecureSheet team makes necessary changes to support business process.

Weeks 2, 3 and 4

Both

8.0

Identify Data Management Requirements

SecureSheet team and client identify process to refresh data in the SecureSheet application.

NOTE: For the audit trail in SecureSheet to track your changes in alignment with how you manage data:

- Once you go live, after rows are added, if you plan to lock out users, export and resort data then reimport, tell SecureSheet Support so we can turn on the setting that will keep cell history aligned with the row unique ID (not the default which is the row number in excel).

Week 4

Both

8.1


Knowledge transfer to client

SecureSheet team transfers knowledge on import/export process to manage data and user changes.

Week 4, 5 or 6

Both

9.0

Refresh Data (if required)

Client clears test data and imports the data set in the same format as SecureSheet with the "go-live" data.

Week 4, 5 or 6

Client

10.0

Final Review and Sign-Off

Client verifies that SecureSheet is complete to client specifications.

Week 4, 5 or 6

Client


11.0

Training

SecureSheet trains key client personnel.  

Client trains end users on SecureSheet.

Client can use all Help content as source to modify for any specific end user instructions.

Typically one to two weeks prior to Go-Live


12.0

Go-Live

Final data is loaded, any test data is cleared.

Go-Live date

Client

12.1


Final review and approval

Client reviews and approves SecureSheet is ready to be opened for users.

Go-Live date

Client

12.2


Activate SecureSheet for users

Client makes the SecureSheet "Active" and notifies users.

Go-Live date

Client

13.0

Post Go-Live Support

SecureSheet is available to help answer/resolve any issues after Go-Live.

Typically Go-Live date plus 1 or 2 weeks



14.0

Lock sheet/rows as required

Lock out different levels as needed through the approval process.

As required

Client

15.0

Reopen SecureSheet/Generate Statements

Reopen SecureSheet to various levels and generate statements (if required).

As required

Both

16.0

Continuous Improvement Process

Client identifies future revisions based on user feedback after Go-Live.

After Go-Live

Client

16.1


Project debrief

SecureSheet supports project debrief as desired to capture insights and lessons learned for future cycles.

Typically 3 weeks post Go-Live

Both